10 ยท Scenario analysis to 2030

How much data centre capacity will Australia have in 2030?

Australian data centres · as at 2026-09-21 · primer pages 61, 62, 63, 66 of 85

Scenario architecture: four drivers decide whether 2030 lands nearer 5 GW or 6.2 GW, and the pipeline sets the upper end

Four drivers decide whether 2030 lands nearer 5 GW or 6.2 GW. The bear, base and bull cases, what each assumes, and why even the bear case is a roughly 3.7x expansion on end-2025 operating capacity.

Operating capacity, GW: published figures above the line, the inashanu 2030 scenario corridor below

1.35 GW
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)
~6 GW required
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)
7.18 GW
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)
5.0 GW
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)
6.0 GW
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)
6.22 GW
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)

Four drivers decide where in the corridor 2030 lands

Power access & policy

AI demand conversion

Cost of capital

Delivery capacity

Anchors (all published)

Anchors (all published). Source: AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025); ITK/CEFC-Baringa (May 2026). As at 21 Sep 2026.
Anchor2030-ish figureWhat it counts
AEMO Step Change AEMO 2025 IASR~6 GW requiredOperating IT load
Mordor capacity forecast Mordor (Jan 2026)7.18 GW (15.25% CAGR)IT load capacity

The base case is the AEMO requirement met. Mordor is carried on its own basis. M3 (~9.5 GW, early 2030s) and CEFC/Baringa (4.7-7.4 GW, 2035) follow overleaf.

All three scenarios accept the demand evidence (Sections 04, 08): they differ on deliverability and financing, not on whether customers want Australian megawatts

The four drivers: bear and bull conditions

The four drivers: bear and bull conditions. Source: AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025); ITK/CEFC-Baringa (May 2026). As at 21 Sep 2026.
DriverBear conditionBull condition
Power access & policyNet-generator costs + NSW prohibitions stall connections; queue stays 8+ yrsREZ-style access schemes accelerate; firming obligations met with BESS at scale
AI demand conversionOpenAI-scale MoUs lapse; inference shifts to edge; US-style construction rollover arrivesMoUs convert to leases; sovereign-AI exemption pulls regional GPU demand to AU
Cost of capitalRates higher-for-longer; NXT-style de-rating spreads; private debt tightensREIT IPO window opens (AirTrunk); superannuation allocations deepen
Delivery capacityTrades competition with housing worsens; 22% senior engineer vacancy persistsIDA fast-tracking holds; modular/prefab lifts throughput

How to use these scenarios

They are planning constructs, not forecasts: each pairs a capacity outcome with the driver conditions that produce it, so a committee can map its own judgement to a number. The probability weights on the watchboard page make our judgement explicit; the driver table above shows what evidence would change it.

Anchors (all published), continued

Anchors (all published), continued. Source: AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025); ITK/CEFC-Baringa (May 2026). As at 21 Sep 2026.
Anchor2030-ish figure
M3 built-out trajectory~9.5 GW by early 2030s
CEFC/Baringa4.7-7.4 GW by 2035
M3 supply gap warningup to 1.7 GW gap even after doubling

Anchors (all published), continued. Source: AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025); ITK/CEFC-Baringa (May 2026). As at 21 Sep 2026.

Bear 5.0 GW
Low end of the 5-8 GW planning band (dossier synthesis, 17 Sep 2026)
Base 6.0 GW
The AEMO Step Change requirement met in full (2025 IASR)
Bull 6.22 GW
Every under-construction megawatt commissions, plus 35% of planned and deferred capacity (project table, Section 05)
29.9Bear
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)
34.8Base
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)
35.7Bull
AEMO 2025 IASR; Mordor (Jan 2026); M3 (Nov 2025)

Base case path: ~6.0 GW operating by 2030, a 4.4x expansion in five years, with the bull only 220 MW above it

Three capacity paths from a common 1.35 GW base, GW

Bear 5.0 GW

Base 6.0 GW

Bull 6.22 GW

Base-case delivery path

2026-27
inashanu estimates; anchors: ITK (May 2026), AEMO 2025 IASR, Mordor (Jan 2026), M3 (Nov 2025)

Committed UC delivers (CDC EC5/6 +108 MW, Laverton first campus 150 MW, Stack MEL01/02), the low-risk tranche; AirTrunk MEL2 targets opening in 2H 2027.

2027-28
inashanu estimates; anchors: ITK (May 2026), AEMO 2025 IASR, Mordor (Jan 2026), M3 (Nov 2025)

CDC's 555 MW contract begins delivering (FY28-29); Marsden Park phases; S7 Phase One (H2 2027 target) if the MoU firms.

2028-30
inashanu estimates; anchors: ITK (May 2026), AEMO 2025 IASR, Mordor (Jan 2026), M3 (Nov 2025)

Second-wave campuses (SYD4, ISPT, Atlas, Horsley Park) deliver into net-generator-compliant power.

1.35 GWOperating, end-2025 (ITK)
inashanu estimates; anchors: ITK (May 2026), AEMO 2025 IASR, Mordor (Jan 2026), M3 (Nov 2025)
~6.0 GWBase case, 2030
inashanu estimates; anchors: ITK (May 2026), AEMO 2025 IASR, Mordor (Jan 2026), M3 (Nov 2025)
4.4xExpansion in five years
inashanu estimates; anchors: ITK (May 2026), AEMO 2025 IASR, Mordor (Jan 2026), M3 (Nov 2025)

What moves the path off base

What moves the path off base. Source: inashanu estimates. As at 21 Sep 2026.

Bear trigger
First ministerial network-access prohibition, or OpenAI MoU lapsing, takes the path toward 5 GW.
Bull trigger
The whole under-construction pool commissioning on schedule, plus a second 500 MW-class contract, takes it to 6.22 GW and no further on announced projects.

Why not simply Mordor's 7.18 GW?

Mordor counts IT load capacity: 3,530 MW in 2025 (Jan 2026), against 1,350 MW of operating IT load here (ITK, 11 May 2026). A rate between those two ends measures the distance between two definitions as well as five years of building. At that ratio, 38.2%, its 2030 figure restates to about 2,746 MW (Section 02).

Why the bull sits so close to the base

The bull is built from the projects that exist: 2,301 MW under construction in full, plus 35% of the 5,892 MW planned and of the 1,450 MW Firmus Southgate balance (Section 05, to 16 Sep 2026). That reaches 6,220 MW, 220 MW above base. The deliverable pipeline carries no dramatic upside; more needs unannounced projects on unallocated power, and neither is an 18-month matter.

Even the bear case is a growth story: 5.0 GW by 2030 is ~3.7x end-2025 operating capacity at ~30% p.a.

07NSW access-scheme decisions
inashanu synthesis, as at 21 Sep 2026

First authorisation/prohibition

The single most powerful siting signal in the market

inashanu probability weights (judgemental)

Bear ~25%

Base ~55%

Bull ~20%

inashanu probability weights (judgemental). Source: inashanu synthesis. As at 21 Sep 2026.

Raises floor
Demand evidence is strong
Caps ceiling
Deliverability screens remove most of the announced pipeline
Widens tails
Policy is mid-rewrite

Weights are committee-discussion inputs; no model produces them.

What the scenario debate is really about

The scenario debate is about the slope of extraordinary growth, and about who owns the deliverable megawatts when the music slows.

The scenario set in one panel (inashanu estimates)

5.0 GWbear 2030, CAGR 29.9%
inashanu synthesis, as at 21 Sep 2026
6.0 GWbase 2030, CAGR 34.8%
inashanu synthesis, as at 21 Sep 2026
6.22 GWbull 2030, CAGR 35.7%
inashanu synthesis, as at 21 Sep 2026
25 / 55 / 20%bear / base / bull weights, judgemental
inashanu synthesis, as at 21 Sep 2026

Sources

  1. AEMO 2025 IASR
  2. Mordor, as at Jan 2026
  3. M3, as at Nov 2025
  4. ITK/CEFC-Baringa, as at May 2026
  5. inashanu estimates
  6. anchors: ITK (May 2026), AEMO 2025 IASR, Mordor (Jan 2026), M3, as at Nov 2025
  7. inashanu synthesis

Related

The full primer is published as an 85-page PDF (download) with the underlying market model as a workbook (download).

This page is one of 30 in Australian data centres: the research, indexed by the question each one answers, with the four pages where the published sources disagree set first.

The research is published by inashanu, a studio that produces fixed-scope market research for Australian private equity, priced and dated before work starts. The sample engagement is this primer in full.

This standard, on your question. Six fixed-price deliverables, A$14,000 to A$45,000 excluding GST, opening at the A$14,000 market map in 10 business days. State the decision and the date it has to be made; the written assessment of whether the evidence base will carry it follows within two business days and carries no charge. Request a brief assessment · the catalogue and its prices.

Source: inashanu price schedule, effective 21 September 2026.