Sydney holds ~60% of built-out capacity and ~65% of the power pipeline: Australia is a two-metro market with policy satellites
Sydney holds around 60% of built-out capacity and around 65% of the power pipeline. Precinct-level detail for Sydney's five clusters, Melbourne's western corridor, and the Canberra, Perth, Brisbane, Adelaide and Tasmanian markets.
Sydney's dominance rests on submarine cable landings, the densest enterprise demand, and Eastern Creek's power-and-land combination. Melbourne's west is the challenger corridor. Canberra is structurally sovereign demand; Brisbane, Perth and Adelaide serve regional, resources and defence niches; Tasmania is the emergent AI-factory frontier.
Revenue share by region, 2025
| Item | Value (%) |
|---|---|
| ACT & NSW | 36.5 |
| VIC & TAS | 24.8 |
| QLD | 16.3 |
| WA | 12.4 |
| NT & SA | 10 |
NSW pipeline scale
44 data centre projects totalling 11.4 GW were in the NSW pipeline at 31 March 2026 (Climate Council/DC Byte), equivalent to nearly four Eraring coal stations. By end-2025 the NSW Government had approved or received SSD applications for 22 facilities totalling 3.67 GW, and in March 2026 the Investment Delivery Authority endorsed 15 projects worth A$51.9bn for prioritised approvals.
- 11.4 GW pipeline 44 projects at 31 Mar 2026, nearly four Eraring coal stations
- 3.67 GW in planning 22 facilities approved or SSD lodged by end-2025
- A$51.9bn prioritised 15 projects endorsed by the Investment Delivery Authority, Mar 2026
The market, schematically
Launceston / Bell Bay
Broome ('Meridien')
Map key
primary hub
major metro
regional presence
AI-factory frontier
Nodes by tier
Nodes by tier. Source: IMARC (2026); Climate Council/DC Byte (Jun 2026); The Good Builder (May 2026); w.media via EcoGPT (27 Mar 2026). As at 21 Sep 2026.
- Primary hubs
- Sydney; Melbourne
Nodes by tier. Source: IMARC (2026); Climate Council/DC Byte (Jun 2026); The Good Builder (May 2026); w.media via EcoGPT (27 Mar 2026). As at 21 Sep 2026.
- Major metros
- Brisbane; Perth
Nodes by tier. Source: IMARC (2026); Climate Council/DC Byte (Jun 2026); The Good Builder (May 2026); w.media via EcoGPT (27 Mar 2026). As at 21 Sep 2026.
- Regional presence
- Canberra; Adelaide
Nodes by tier. Source: IMARC (2026); Climate Council/DC Byte (Jun 2026); The Good Builder (May 2026); w.media via EcoGPT (27 Mar 2026). As at 21 Sep 2026.
- AI-factory frontier
- Launceston / Bell Bay (AI Factory Zone); Broome ('Meridien', proposed)
Read-across
Two primary hubs on the south-east seaboard carry the market; every other node is a policy or niche satellite (sovereign Canberra, cabled Perth, fastest-growing Brisbane, defence Adelaide), with the AI-factory frontier at Bell Bay and Broome.
Sydney's growth has consolidated into five precincts: Eastern Creek/Huntingwood is now the largest operating cluster in the country
Eastern Creek / Huntingwood: the operating base
The precincts
- Eastern Creek / Huntingwood: AirTrunk SYD3 (~330-400 MW operating, Australia's largest single operating campus); CDC Eastern Creek (200+ MW operating, EC5/6 adding 108 MW); NEXTDC S7 (612 MW proposed; OpenAI MoU); Goodman 'Project Atlas' (~500 MW proposed); Stack Erskine Park; AWS ~80 MW (est.).
- Kemps Creek / Mamre Road: AirTrunk SYD4 (up to 1.2 GW planned; land A$780m Nov 2025); ISPT campus (~A$5bn, up to 1 GW across six buildings); Microsoft ~100 MW UC.
- Marsden Park: CDC 504 MW approved Nov 2025, scalable to ~1 GW, billed as the Southern Hemisphere's largest.
- Horsley Park: NEXTDC S4 (~300 MW planned; record 250 MW contract); Stack A$3.7bn / 450 MW application.
- Macquarie Park & north: Macquarie DC IC3 Super West (63 MW); Stockland hyperscale approval (Feb 2026); NEXTDC S1-S3, S6 Artarmon 'AI Factory'.
- City fringe: Wetherill Park (Stockland/EdgeConneX 160 MW), Minchinbury (Starwood/Doma), Norwest (GreenSquareDC A$1.2bn, 110 MW), Ultimo (DigiCo SYD1, 88 MW on completion).
Selected announced Sydney capacities, MW IT
| Item | Value |
|---|---|
| AirTrunk SYD4 Mamre Rd/Kemps Creek (1,200 MW, planned) | 1200 |
| ISPT Kemps Creek campus (1,000 MW, announced) | 1000 |
| NEXTDC S7 Eastern Creek, OpenAI MoU (612 MW, in assessment) | 612 |
| CDC Marsden Park, scalable ~1,000 (504 MW, SSD approved) | 504 |
| Goodman ‘Project Atlas’ Eastern Creek (500 MW, SEARS filed) | 500 |
| Stack Horsley Park (450 MW, application) | 450 |
| NEXTDC S4 Horsley Park (300 MW, early works) | 300 |
| Stockland/EdgeConneX Wetherill Park (160 MW, UC) | 160 |
| GreenSquareDC SYD1 Norwest (110 MW, announced) | 110 |
| Macquarie DC IC3 Super West (63 MW, UC) | 63 |
Melbourne's west is a deliberate power play: the Truganina–Laverton–Derrimut corridor anchors on AusNet's Deer Park terminal
- Truganina Stack MEL01 (180 MW) and MEL02 (252 MW); ~1 GW-substation mega-project mooted
- Laverton CDC Laverton 450 MW planned (150 MW first campus UC), ground broken Feb 2025
- Derrimut AirTrunk MEL1 185+ MW, PUE 1.15
- AusNet's Deer Park terminal the power anchor of the west corridor
Pipeline by status
Pipeline by status. Source: Next West Observer (3 Aug 2026); ITK Research (May 2026); JLL Melbourne H1 2025 (13 Oct 2025); W.Media (2026); Max Qi (30 Jul 2026); Allens (2025); DataCenterMap (2026). As at 21 Sep 2026.
- Operating / expanding
- CDC Brooklyn (150+ MW; 350+ at completion); AirTrunk MEL1 Derrimut (185+ MW, PUE 1.15); NEXTDC M3 West Footscray (225 MW planned; 40 MW built); Stack MEL01 Truganina (180 MW; A+B operating); Microsoft Cawley Road; Vantage MEL1 (48-64 MW); Equinix ME1/2/4; ResetData AI-F1 Docklands (Australia's first public 'AI factory').
Pipeline by status. Source: Next West Observer (3 Aug 2026); ITK Research (May 2026); JLL Melbourne H1 2025 (13 Oct 2025); W.Media (2026); Max Qi (30 Jul 2026); Allens (2025); DataCenterMap (2026). As at 21 Sep 2026.
- Under construction
- CDC Laverton (450 MW planned; ground broken on the 150 MW first campus Feb 2025); Stack MEL02 (252 MW, shell complete); NEXTDC M4 Fishermans Bend (A$2bn liquid-cooled AI factory); AirTrunk MEL2 (354+ MW, A$5bn+; site acquired Dec 2025, opening targeted 2H 2027).
Pipeline by status. Source: Next West Observer (3 Aug 2026); ITK Research (May 2026); JLL Melbourne H1 2025 (13 Oct 2025); W.Media (2026); Max Qi (30 Jul 2026); Allens (2025); DataCenterMap (2026). As at 21 Sep 2026.
- AI factories
- Firmus Southgate Melbourne phase 1: 150 MW, ~18,400 Nvidia GB300 GPUs, A$4.5bn, online 2026, backed by a multi-billion-dollar contract.
Pipeline by status. Source: Next West Observer (3 Aug 2026); ITK Research (May 2026); JLL Melbourne H1 2025 (13 Oct 2025); W.Media (2026); Max Qi (30 Jul 2026); Allens (2025); DataCenterMap (2026). As at 21 Sep 2026.
- Approvals momentum
- 171 Leakes Rd permitted 2025; 1 Oroya Dr permitted May 2026; 433 Mt Atkinson Rd applied Jul 2026; a ~1 GW-substation Truganina mega-project mooted; 250 MVA at Cherry Lane applied May 2026.
Pipeline by status. Source: Next West Observer (3 Aug 2026); ITK Research (May 2026); JLL Melbourne H1 2025 (13 Oct 2025); W.Media (2026); Max Qi (30 Jul 2026); Allens (2025); DataCenterMap (2026). As at 21 Sep 2026.
- Brownfield power
- Keppel's proposed 720 MW campus on 123 ha at the former Hazelwood power station, the template for generator-site conversion.
Selected Melbourne capacities, MW IT
| Item | Value |
|---|---|
| Keppel Hazelwood Latrobe Valley (720 MW, proposed) | 720 |
| CDC Laverton Campus 1+2 (450 MW planned) | 450 |
| AirTrunk MEL2 (354 MW, opening 2H 2027) | 354 |
| Stack MEL02 Truganina (252 MW, shell complete) | 252 |
| NEXTDC M3 West Footscray (225 MW, 40 MW built) | 225 |
| Firmus Southgate MEL ph.1 (150 MW, 2026) | 150 |
| Vantage MEL1 (48–64 MW) | 64 |
| ResetData AI-F1 Docklands (small, operating) | 10 |
Beyond the big two: sovereign Canberra, cabled Perth, fastest-growing Brisbane, defence Adelaide
Canberra: the sovereign hub
CDC's original campuses (Hume, Fyshwick) anchor federal government demand under the Hosting Certification Framework; Microsoft/CDC ~60 MW (EcoGPT tracking). Macquarie Data Centres' Canberra campus is Certified Strategic and claims a material share of government workloads; NEXTDC C1 completes the set.
Canberra's ceiling is demand-driven rather than power-driven: growth follows whole-of-government cloud mandates, including the Whole-of-Government Cloud Computing Policy effective July 2026.
Brisbane: fastest-growing region
NEXTDC B1/B2 (B2 expansion under way); Quinbrook's 'Supernode' at Brendale pairs a data centre campus with grid-scale storage, the energy-integrated model the net-generator policy will push mainstream. Queensland grows at ~6.8% CAGR (IMARC), the fastest of any region, with edge deployments riding the 5G rollout.
Adelaide: defence-driven
NEXTDC A1 opened ~late 2024; DCI (Brookfield) operates at Kidman Park. NT & SA combined hold ~10.0% revenue share, with defence-industry demand the swing factor.
Perth: cable-landing advantage
AirTrunk PER1; NEXTDC P1/P2; Equinix PE1/PE2. PE2 is the landing station for the Australia-Singapore Cable and the Oman Australia Cable, making Perth Australia's lowest-latency gateway to Asia and the Middle East. WA holds 12.4% revenue share on resources-sector and subsea demand.
Frontier: Project Meridien
A proposed 1 GW facility on Karajarri country south of Broome would put Australia in the global top power class; early-stage, but a marker of where land-plus-power economics point.
Regional scoreboard
Each satellite metro turns on one swing factor named above: whole-of-government cloud mandates in Canberra, energy-integrated campuses and 5G edge in Brisbane, subsea cable landings in Perth, and defence-industry demand in Adelaide.
Tasmania is the structural surprise: cool climate, hydro-wind firming and a world-first AI Factory Zone
Metro positioning summary (inashanu synthesis)
- AI Factory Zone (Jul 2025): world-first designation in Northern Tasmania clearing the path for Firmus's Project Southgate.
- Bell Bay: former Gunns pulp mill site; ~288 MW draw, up to 400 MW planned statewide; ~10 days/year of water cooling and ~99% less water than a typical data centre.
- Mainland pairing: Southgate couples Tasmanian campuses with CDC-partnered mainland sites and a 150 MW Melbourne phase 1; Firmus targets 1.6 GW by 2028, financed by a US$10bn Blackstone/Coatue debt facility (Feb 2026) and >US$10.5bn post-money equity (Aug 2026).
Why it matters
Tasmania tests whether Australia's energy constraint can be arbitraged: dispatchable-load AI factories co-located with renewables could undercut metro power costs while satisfying net-generator rules by design. Watch water, transmission and whether GPU customers accept latency to Hobart.
| Metro | Role | Binding constraint |
|---|---|---|
| Sydney | National anchor; hyperscale + enterprise | Power queue; land price (~A$1,500/sqm+) |
| Melbourne | Second corridor; AI factories | West-corridor grid concentration |
| Canberra | Sovereign government demand | Certified Strategic supply; HCF reform |
| Brisbane | Fastest growth; energy-integrated | Scale of anchor tenants |
| Perth | Asia/Middle East gateway | Distance from east-coast demand |
| Adelaide | Defence niche | Market depth |
| Tasmania | AI-factory frontier | Transmission; customer latency acceptance |
Project Southgate in numbers
Sources
- IMARC, as at 2026
- ResearchAndMarkets via Business Wire, as at 16 Jul 2025
- Climate Council/DC Byte, as at Jun 2026
- The Good Builder, as at 6 May 2026
- w.media via EcoGPT, as at 27 Mar 2026
- The Good Builder, as at May 2026
- ITK Research top-10 UC, as at 11 May 2026
- NSW Planning Portal, as at Nov 2025
- iEnvironmental, as at 16 Jun 2026
- Troview, as at 29 Jun 2026
- DCD, as at 4 Sep 2026
- Next West Observer, as at 3 Aug 2026
- ITK Research, as at May 2026
- JLL Melbourne H1 2025, as at 13 Oct 2025
- W.Media, as at 2026
- Max Qi, as at 30 Jul 2026
- Allens, as at 2025
- DataCenterMap, as at 2026
- Canberra: EcoGPT, as at Apr 2026
- Macquarie Data Centres
- Performance AI prospectus. Brisbane: ITK Research, as at May 2026
- Rod Terry/LinkedIn (Jul 2026). Perth: Submarine Networks (OAC)
- IMARC (2026). Frontier: The Good Builder, as at May 2026
- Firmus, as at 2 Jul 2025
- Firmus Bell Bay FAQs, as at Sep 2025
- DCD, as at 9 Feb 2026
- Yahoo/Verdict, as at 10 Aug 2026
- sources as per metro pages
Related
- How much electricity do Australian data centres use?
- What is data centre land worth in Australia?
- What is in Australia's data centre development pipeline?
- Who are the largest data centre operators in Australia?
The full primer is published as an 85-page PDF (download) with the underlying market model as a workbook (download).
This page is one of 30 in Australian data centres: the research, indexed by the question each one answers, with the four pages where the published sources disagree set first.
The research is published by inashanu, a studio that produces fixed-scope market research for Australian private equity, priced and dated before work starts. The sample engagement is this primer in full.
This standard, on your question. Six fixed-price deliverables, A$14,000 to A$45,000 excluding GST, opening at the A$14,000 market map in 10 business days. State the decision and the date it has to be made; the written assessment of whether the evidence base will carry it follows within two business days and carries no charge. Request a brief assessment · the catalogue and its prices.